Pre-Installation Checklist: What You Need Before You Start
Installing a submersible pump is a precision task that requires proper planning and the right equipment. Rushing this process can result in damaged equipment, personal injury, or a pump that fails within months. Here is what you need before you begin:
Essential Equipment and Tools
- Crane, tripod, or winch with sufficient lifting capacity (pump + water-filled pipe + safety factor of 1.5x)
- Torque arrestor (sized for your casing diameter)
- Submersible drop cable with water-blocking construction
- Stainless steel cable ties (NOT plastic — they become brittle underwater)
- Cable guards / centralizers (every 3-5 meters on the drop pipe)
- Pipe joint compound or PTFE tape for threaded connections
- Check valve(s) — spring-loaded type for vertical installations
- Multimeter for continuity and insulation testing
- Water level meter to verify static level and drawdown
- Safety harness, hard hat, and protective gloves
Step 1: Well Preparation and Inspection
Before lowering anything into the well, complete these critical checks:
- Measure the well depth — Use a weighted measuring line to confirm total depth and compare with the driller's log
- Measure static water level — This is your baseline for setting pump depth and calculating drawdown
- Inspect the casing — Use a downhole camera if available, or lower a dummy pipe to check for obstructions, offsets, or casing damage
- Verify casing diameter — Measure the ID at multiple depths; a 6-inch casing can vary by 3-5mm
- Flush the well — If the well has been idle, flush with clean water at high volume to remove settled sediment
- Check wellhead condition — Ensure the wellhead seal, base plate, and vent are in good condition
Step 2: Pump Assembly and Testing
Assemble and test the pump above ground before lowering it into the well:
- Motor lead connection — Connect the drop cable to the motor leads using waterproof heat-shrink splice kits. Never use standard electrical tape — it will fail underwater.
- Insulation test — Using a megohmmeter (megger), test insulation resistance between each phase and ground. Minimum acceptable: 20 megohms for a new motor, 2 megohms for used.
- Check free rotation — Manually rotate the pump shaft to confirm smooth, free movement with no binding or scraping.
- Attach torque arrestor — Mount the torque arrestor directly above the pump. This absorbs starting torque and prevents the pump from twisting the cable against the casing wall.
- Install check valve — A spring-loaded check valve should be installed immediately above the pump discharge. For installations deeper than 100m, install additional check valves every 60-80m on the riser pipe.
Step 3: Lowering the Pump Assembly
| Depth below surface | Action | Check |
|---|---|---|
| 0-5 meters | Lower slowly, check for obstructions | Verify cable is not twisting |
| 5-10 meters | Install first cable guard | Cable slack: 2-3cm between guards |
| Every 3 meters | Install cable guards / centralizers | Prevent cable from contacting casing |
| Every pipe joint | Apply thread compound, torque to spec | No cross-threading, no leaks |
| At target depth | Set pump 3-5m above well screen | Confirm depth with measuring tape |
Critical safety rules during lowering:
- NEVER lift the pump by the electrical cable — always use the pipe or a lifting bail
- Maintain constant tension on the cable to prevent slack loops that can kink or abrade
- Lower at a steady pace — sudden drops can damage motor bearings
- If the pump binds or stops, DO NOT force it — pull back up 1-2 meters and try again
Step 4: Surface Electrical Connections
- Install a dedicated circuit breaker — Properly sized for motor full-load current plus 25% (per NEC/ IEC standards)
- Motor protection relay — Install overload protection with phase failure and phase sequence protection for three-phase motors
- Ground the system — Connect the motor ground to a proper grounding electrode. Never use the well casing as the sole ground path.
- Voltage check — Measure voltage at the motor leads (at the surface). Voltage must be within +/-10% of motor nameplate rating under load.
Step 5: Commissioning and Startup
- Slow fill the riser pipe — If the check valve prevents backfilling, slowly pour water into the pipe to prime the pump
- Momentary start (1-2 seconds) — Verify correct rotation direction. A pump running backward produces ~50% flow and can unscrew threaded connections
- Monitor startup current — Inrush should be 4-7x FLA for less than 1 second, then stabilize
- Measure flow rate and pressure — Compare with the pump performance curve. Flow within 10% of curve = correct installation
- Record baseline data — Static water level, pumping water level, flow rate, discharge pressure, voltage, and current at full flow. This is your reference for future troubleshooting.
Installation not going as planned? NOVAPUMP provides remote installation guidance and can connect you with certified pump installers in your region. Contact our technical support team for assistance.